Annandale High School - Renewal & Additions, Phase 2

Project Details

Owner: Fairfax County Public Schools
Contract Amount: $16,757,930
Date of Award: January 2001
Anticipated Date of Completion: June 2003
Architect: Beery, Rio & Associates, Springfield, VA

Photo Photo

This project includes the renovation of approx. 155,000 SF of space with 28,000 SF of additions. New additions primarily include:

Renovated spaces include new science labs, classrooms and media center, as well as upgraded mechanical and electrical utility rooms. Exterior work includes new athletic support structures, football field bleacher rehab and new football and baseball field lighting.