New Executive Office Building — Fire and Life Safety Upgrade

Project Details

Owner: General Services Administration
Contract Amount: $6,324,176
Date of Award: September 1992
Date of Completion: February 1995
Architects: Halliburton NUS Environmental Corporation

Photo

This project involved the installation of sprinkler, fire alarm, lighting and ceiling systems in an occupied, highly-secured government building. Areas were fully occupied and work was performed on weekends only.

On Friday evenings, Grunley videotaped the furnishings of the offices, moved furniture, contained space, removed asbestos contained ceilings, and installed a new wet pipe sprinkler system, a new fire alarm system, light fixtures with air boots, a new suspension system and new ceilings.

Work was followed by the complete clean-up and furniture relocation to accommodate the government's full use every Monday morning.