National Airport FaCade and Window Repair

Project Details

Owner: Metropolitan Washington Airports Authority
Contract Amount: $9,207,321
Date of Award: 8/31/06; Admin NTP - 11/8/06; Construction NTP - 3/5/07
Date of Completion: August 29, 2008
Architect: Shalom Baranes Associates
Washington, DC

Grunley Construction provided façade renovation, restoration, and replacement services at the original 1940's circa Terminal of Ronald Reagan Washington National Airport. The scope of the project included:

The building remained occupied throughout the construction process. Portions of work were performed at night.

Date Posted: September 24, 2008